Project description

The City will be carrying out redevelopment works on Rue du Pont in Beggen (municipality of Walferdange). These works are being done in cooperation with:

  • VDL – Service Voirie (Department of Streets): Complete upgrade of the thoroughfare and public spaces on Rue du Pont. Installation of a Vel'OH! station.
  • VDL – Service Eaux (Water Department): Replacement of the principal water main and deteriorated connections to homes.
  • VDL – Service Éclairage public (Public Lighting Department): Replacement of cables for public lighting systems and street lights. Upgrade of electrical cabinets to bring them up to code. Installation of special lighting at pedestrian crossings to improve visibility of pedestrians.
  • VDL – Service Canalisation (Sewer Department): The rainwater pipes will be replaced for hydraulic reasons along the entire length of Rue du Pont. Installation of a new connection between the two main wastewater drains, from Rue de Beggen and the water treatment plant.
  • VDL – TIC (ICT Department): Upgrade and extension of the fibre-optic network and the City of Luxembourg's Wi-Fi network. Connection of the water treatment plant to the City's network. Upgrade of electrical cabinets to bring them up to code by placing an electricity meter between the mains and the ICT network.
  • Creos Luxembourg SA Gaz:Replacement of the low-pressure gas network on Rue du Pont. Connection of homes to the new gas mains.
  • Post Luxembourg:Extension of the high-speed fibre-optic broadband network on Rue Beggen to the existing structures on Rue du Pont.

Works schedule

Commencement of work: September 2024

Expected duration of the works: 175 working days

Planned completion: July 2025

Traffic information

For vehicular traffic:

The affected sections will be closed to traffic in phases as the project progresses. Pedestrian access and access for emergency services will be guaranteed throughout the duration of the works. Vehicular access to private property will be maintained as long as physically possible.

For businesses and deliveries:

The City of Luxembourg will try to ensure access for deliveries to local businesses throughout the duration of the works. As construction progresses, there will be changes to traffic flow in this area.

Your home utility connections

  • As part of the construction project, City representatives and private contractors will visit residents' homes.
  • They will be assessing the condition of their existing connections.
  • If you wish to have your existing connections replaced, please inform the City representatives during this on-site inspection.

If you experience a malfunction in your gas, water or communication system, please contact the 24-hour hotlines listed below.

  • Service Eaux – Tel.: 4796-2883
  • Creos Électricité – Tel.: 8002-9900
  • Creos Gaz – Tel.: 8007-3001
  • Post Luxembourg – Tel.: 8002-8004
  • Eltrona – Tel.: 499 466 888

Stay informed

To make life easier for residents while these works are being carried out, the City of Luxembourg has implemented a series of measures, including the option to participate in meetings regarding the progress of the work. Residents affected by the works may participate in these meetings to obtain additional information about the project's progress and air any grievances they may have.

Weekly site meetings

Meetings will be held every Friday at 9:30 at the worksite.

Contacts for this project

Department Contact Telephone number
VDL – Service Coordination des chantiers (Work-Site Coordination Department) Laura Sertic 4796 2803
VDL – Service Eaux (Water Department) Carole Kirch 4796 4304
VDL – Service Éclairage public (Public Lighting Department) Karim Ainahi 4796 3883
VDL – Service TIC (ITC Department) Jo Petit 4796 3838
VDL - Service Canalisation (Sewer Department) Marc Gilson 4796 2775
VDL – Construction Mediators chantiers@vdl.lu 4796 4343
VDL – Service Voirie (Department of Streets) Nathalie Pires 4796 2331
CREOS Gaz Carlos Simoes 2624 5816
POST Technologies Armand Kruse 621 191 339