Project description
The City is carrying out infrastucture works in Odendahl Park. These works are being carried out in collaboration with the following municipal departments:
- VDL – Service Eaux (Water Department): Installation of a public water supply network in Odendahl Park to improve access in the Pfaffenthal district. This network will also enable the supply of drinking water during the Luxembourg Urban Garden (LUGA) show.
- VDL – Éclairage public (Public Lighting Departing): Upgrading of the street lighting network in the western part of the park.
- VDL – TIC (ICT Department): Rollout of the fibre optic network in Odendahl Park.
Works schedule
Commencement of work: autumn 2024
Expected duration: 100 working days
Planned completion: Spring 2025
Traffic information
The works will be carried out in several phases. The affected sections will be gradually closed off to pedestrian traffic as the project progresses.
Site detours for pedestrians and cyclists will be put in place throughout the various phases. After the collective winter leave, which ends on 15 January 2025, the entrance to the park on the Rue Vauban /
Progress to date
Which works are currently being carried out?
The contractor is currently laying the drinking water mains to ensure supply for the LUGA.
Stay informed
Weekly site meetings
A meeting will be held on site every Wednesday at 11:00.
Contacts for this project
Department | Contact | Telephone number |
---|---|---|
Service Eaux | Tom Wagner | 4796-4334 |
Construction mediators | chantiers@vdl.lu | 4796-4343 |
Geri Management (health and safety) | Catarina Duarte | 671 154 277 |