Project description

The City will be carrying out redevelopment works on Rue N.S. Pierret. These works are being done in cooperation with:

  • VDL – Service Voirie (Department of Streets): Redevelopment of the road superstructure (parking bays, tree pits and pedestrian walkway redevelopment).
  • VDL – Service Eaux (Water Department): Complete replacement of the main water distribution line and replacement of home water supply lines that have deteriorated.
  • VDL – Service Éclairage public (Public Lighting Department): Replacement and upgrade of the public lighting system, and replacement of street lamps. Installation of special lighting at pedestrian crossings to improve visibility of pedestrians.
  • VDL – Service Canalisation (Sewer Department): Replacement of the rainwater and wastewater drains.
  • Creos Luxembourg SA Electricité: Replacement and upgrade of the low-voltage grid, which is insufficient in its current design and generally in a state of deterioration. Replacement of home utility connections. Upgrade of public lighting connections and Creos electrical grids with VDL electric metre boxes.
  • Creos Luxembourg SA Gaz: Complete replacement of the main gas supply line and home gas supply connections.
  • Post Luxembourg: Replacement of old cables with high-speed fibre-optic ones, and replacement of home utility connections.

Works schedule

Commencement of work: October 2024

Expected duration of the works: 250 working days

Planned completion: autumn 2025

Traffic information

For vehicular traffic:

Rue N.S. Pierret will be closed to traffic except for local residents and suppliers/deliveries. Pedestrian access and access for emergency services will be guaranteed throughout the duration of the works. Vehicular access to private property will be maintained as long as physically possible.

For businesses and deliveries:

The City of Luxembourg will try to ensure access for deliveries to local businesses throughout the duration of the works.

As construction progresses, there will be changes to the flow of traffic in this area.

Your home utility connections

  • As part of the construction project, City representatives and private contractors will visit residents' homes.
  • They will be assessing the condition of their existing connections.
  • If you wish to have your existing connections replaced, please inform the City representatives during this on-site inspection.

If you experience a malfunction in your gas, water or communication system, please contact the 24-hour hotlines listed below.

  • Service Eaux – Tel.: 4796-3003
  • Creos Électricité – Tel.: 8002-9900
  • Creos Gaz – Tel.: 8007-3001
  • Post Luxembourg – Tel.: 8002-8004

Stay informed

To make life easier for residents while these works are being carried out, the City of Luxembourg has implemented a series of measures, including the option to participate in meetings regarding the progress of the work. Residents affected by the works may participate in these meetings to obtain additional information about the project's progress and air any grievances they may have.

Weekly site meetings

The date will be published shortly.

Contacts for this project

Department Contact Telephone number
VDL – Service Coordination des chantiers (Work-Site Coordination Department) Martine Fey 4796 2804
VDL – Service Voirie (Department of Streets) Sebastian Schinner 4796 3879
VDL – Service Eaux (Water Department) Laurent Di Boneventura 4796 3858
VDL – Service Éclairage public (Public Lighting Department) Karim Ainahi 4796 3883
VDL – Construction Mediators chantiers@vdl.lu 4796 4343
CREOS Électricité Chris Olinger 2624 5781
CREOS Gaz Diane Hoffmann 2624 5819
POST Technologies Dino Baiocchi 2424 5031