Project description
The City will be carrying out redevelopment works on Rue Nicolas Adames. These works are being done in cooperation with:
- VDL – Service Voirie (Department of Streets): Complete rebuild of the superstructure. Planting of 12 new trees and replacement of old benches.
- VDL – Service Eaux (Water Department): Replacement of the water main and a number of home connections.
- VDL – Service Circulation (Traffic Department): Changes to traffic light posts at crosswalks.
- VDL – Service Éclairage public (Public Lighting Department): Replacement of public lighting.
- VDL – Service TIC (ICT Department): Replacement of existing networks.
- Creos Luxembourg SA Electricité: Replacement of the low-voltage/medium-voltage grids, and replacement of a number of connections to houses.
Works schedule
Commencement of work: January 2024
Expected duration of the works: 250 working days (from 7:00 to 17:00)
Planned completion: February 2025
Traffic information
What is the current traffic situation?
For cars and pedestrians:
Parking spots will be removed as the works progress. In the event of any changes to vehicle access, appropriate signage will be put in place.
For businesses and deliveries:
The City of Luxembourg will try to ensure access for deliveries to local businesses throughout the duration of the works. As construction progresses, there will be changes to the flow of traffic in this area.
Your home utility connections
- As part of the construction project, City representatives and private contractors will visit residents' homes.
- To assess the condition of their existing connections.
- If you wish to have your existing connections replaced, please inform the Luxembourg City representatives during this on-site inspection.
If you have any problems with your gas, water or communications networks, please contact the services below, which are open 24/7:
- Service Eaux – Tel.: 4796-2883
- Creos Électricité – Tel.: 8002-9900
- Creos Gaz – Tel.: 8007-3001
Stay informed
To make life easier for residents while these works are being carried out, the City of Luxembourg has implemented a series of measures, including the option to participate in meetings regarding the progress of the work. Residents affected by the works may participate in these meetings to obtain additional information about the project's progress and present any complaints they may have.
Weekly site meetings
The date of the meeting will be publicised shortly.
Contacts for this work site
DEPARTMENT | CONTACT | TELEPHONE NUMBER |
---|---|---|
VDL – Service Coordination des chantiers | Laura Sertic | 4796-2803 |
VDL – Service Eaux | Tom Wagner | 4796-4334 |
VDL – Service TIC | Jo Petit | 4796-3838 |
VDL - Service Éclairage | Karim Ainahi | 4796-3883 |
VDL – Service Circulation | Julien Bertolotti | 4796-3339 |
VDL – Service Canalisation | Katarina Pecirep | 4796-3072 |
VDL – Service Voirie | Tiago Mesquita | 4796-4753 |
CREOS Electricité | Jerome Lemmer | 2624-5100 |