Project description

The City will soon be carrying out redevelopment works on Rue de Gasperic. These works are being done in cooperation with:

  • VDL – Service Voirie (Department of Streets)
  • VDL – Service Eaux (Water Department)
  • VDL – Service Éclairage public (Public Lighting Department)
  • VDL – Service Technologies de l'information et de la communication (Information and Communication Technology Department) 
  • VDL – Service Circulation (Traffic Department)
  • VDL – Service Canalisation (Sewer Department)
  • Creos Luxembourg SA Electricité
  • Creos Luxembourg SA Gaz

Works schedule

  • Commencement of work: Early 2025
  • Expected duration of the works: 425 working days
  • Planned completion: winter of 2026

Traffic information

What is the current traffic situation?

For vehicular traffic

The affected sections will be gradually closed off to traffic as the project progresses.

Pedestrian access and access for emergency services will be guaranteed throughout the duration of the works. Vehicular access to private property will be maintained as long as physically possible.

For businesses and deliveries:

The City of Luxembourg will try to ensure access for deliveries to local businesses throughout the duration of the works.

As construction progresses, there will be changes to the flow of traffic in this area. Appropriate signage will be erected by the Service Circulation (Traffic Department). The City of Luxembourg thanks local residents and businesses, as well as road users, for their understanding regarding any potential inconveniences.

Stay informed

To make life easier for residents while these works are being carried out, the City of Luxembourg has implemented a series of measures, including the option to participate in meetings regarding the progress of the work. Residents affected by the works may participate in these meetings to obtain additional information about the project's progress and present any complaints they may have.

Your home utility connections

  • As part of the construction project, City representatives and private contractors will visit residents' homes.
  • To assess the condition of their existing connections.
  • If you wish to have your existing connections replaced, please inform the Luxembourg City representatives during this on-site inspection.

If you have any problems with your gas, water or communications networks, please contact the numbers below. These lines are open 24/7:

  • Service Eaux (Water Department) – Tel.: 4796-2883
  • Creos Électricité – Tel.: 8002-9900
  • Creos Gaz – Tel.: 8007-3001
  • Post Luxembourg – Tel.: 8002-8004
  • Eltrona - Tel.: 499 466 888

Contacts for this work site

DEPARTMENT CONTACT TELEPHONE NUMBER
VDL – Service Coordination des chantiers (Work Site Coordination Department) Dan Mathes 4796-2822
VDL – Construction Mediators chantiers@vdl.lu 4796-4343