Project description

The City is carrying out upgrade and redevelopment works on Rue Adolphe and Rue de Vianden. These works are being done in cooperation with:

  • VDL – Service Voirie (Roads Department): Redevelopment of the road superstructure on Rue Adolphe and Rue de Vianden (parking lanes, tree pits, pedestrian walkways).
  • VDL – Service Canalisation (Sewer Department): Replacement of the deteriorated sanitary sewer and construction of a flow diversion system at the intersection of Rue de Vianden and Rue Alphonse Munchen.
  • VDL – Service Eaux (Water Department): Complete replacement of the main water distribution line and replacement of home water supply lines that have deteriorated.
  • VDL – Service Éclairage public (Public Lighting Department): Replacement and upgrade of the public lighting system, and replacement of street lamps. Installation of a new "Remote management" network.
  • VDL – Service TIC (ICT Department – network and communications): Upgrade and rollout of the fibre-optic network and extension of Luxembourg City's WIFI network.
  • VDL – Service Parcs (Parks Department): Redevelopment of green spaces.
  • Creos Luxembourg SA Electricité: Replacement and extension of the low- and high-voltage power network, which is insufficient in its current design and generally in a state of deterioration. Replacement of home utility connections. Upgrade of public lighting connections and Creos electrical grids with VDL electric metre boxes.
  • Creos Luxembourg SA Gaz: Complete replacement of the main gas supply line and replacement of deteriorated home gas supply lines.
  • Post Luxembourg: Replacement of FTTH (Fibre To The Home) lines and installation of backup ducts.
  • Eltrona: Removal of façade-mounted cable systems and replacement of existing cable networks.

Works schedule

Commencement of work: Spring 2023

Expected duration of the works: 410 working days

Planned completion: Spring 2025

Traffic information

What is the current traffic situation?

For vehicular traffic:

The roadworks will be carried out in sections. These four sections will be closed to traffic one at a time, based on how the works progress.

Pedestrian access and access for emergency services will be guaranteed throughout the duration of the works. Vehicular access to private property will be maintained as long as physically possible. Certain parking spots will be removed as the works progress.

For businesses and deliveries:

The City of Luxembourg will try to ensure access for deliveries to local businesses throughout the duration of the works. As construction progresses, there will be changes to traffic flow in this area.

For public transport users:

No changes.

Progress to date

What work has already been completed?

The first two sections have been finished, and the installation of utility networks in the third section has also been completed.

What work remains to be done?

In the third section, superstructure work and some crossings remain to be completed. The sewerage, water supply, dry utilities and superstructure work on the fourth section also need to be completed.

Your home utility connections

  • As part of the construction project, City representatives and private contractors will visit residents' homes.
  • To assess the condition of their existing connections.
  • If you wish to have your existing connections replaced, please inform the Luxembourg City representatives during this on-site inspection.

If you experience a malfunction in your gas, water or communication system, please contact the 24-hour hotlines listed below.

  • Service Eaux – Tel.: 4796-2883
  • Creos Électricité – Tel.: 8002-9900
  • Creos Gaz – Tel.: 8007-3001
  • Post Luxembourg – Tel.: 8002-8004
  • Eltrona – Tel.: 499 466 888

Stay informed

To make life easier for residents while these works are being carried out, the City of Luxembourg has implemented a series of measures, including the option to participate in meetings regarding the progress of the work. Residents affected by the works may participate in these meetings to obtain additional information about the project's progress and air any grievances they may have.

Weekly site meetings

A meeting will be held on site every Tuesday at 9:30. 

Information session

An information session for local residents was held on 15 November 2022. A presentation of this development project is available below.

Contacts for this project

4796-2518
Department Contact Telephone number
VDL – Service Coordination des chantiers Laura Sertic 4796-2803
VDL – Service Canalisation Gilles Cecchetto
VDL – Service Voirie    Bob Bremer 4796-3032
VDL – Service Eaux      Tom Wagner 4796-4334
VDL – Service Éclairage Public Kim Weijs 4796-3884
VDL – Service TIC         Jo Petit 4796-3838
VDL – Service Circulation   Edvin Hajder 4796-2319
VDL – Construction Mediators chantiers@vdl.lu  4796-4343
CREOS Gaz     Gilles Garganese 26245839
CREOS Electricité Claude Almeida 26245727
POST  Marc Mersch 24245743